Critical Path Method.

Spend three acceleration tokens on a six-task project and try to launch sooner.

Interactive experimentintuitiveField note ·
Preparing the experiment…
THE SHORT VERSION

Critical Path Method, explained.

A critical path is a longest dependency path through a project network; its duration determines the earliest project completion under the schedule assumptions.

01 / THE MECHANISM

Why it happens

Tasks A–F last 3,4,2,5,3,2 days. A precedes C and D; B precedes E; C,D,E precede F. Forward and backward passes compute earliest finishes and slack. Each of three tokens shortens a task by one day, to a minimum of one.

A critical path is a longest dependency path through a project network; its duration determines the earliest project completion under the schedule assumptions.

Read the result

Zero slack identifies current timing constraints. Recompute after each token because shortening one path can make another path equally important.

02 / FOLLOW IT THROUGH

A worked example

Three tokens before launch

  1. The initial A–D–F path lasts ten days, while B–E–F lasts nine. Task C has spare time.

  2. Spend a token shortening C and observe that the project duration stays ten, despite a real improvement to that task.

  3. Reset and shorten D instead. Launch falls to nine days, at which point another dependency path also constrains completion.

OPTIONAL DEEPER DETAILGo deeper: inside the model

Inside this model

Tasks A–F last 3,4,2,5,3,2 days. A precedes C and D; B precedes E; C,D,E precede F. Forward and backward passes compute earliest finishes and slack. Each of three tokens shortens a task by one day, to a minimum of one.

03 / BEYOND THE EXPERIMENT

Where this idea is useful

A practical use

A team can avoid accelerating a task that already has slack while the actual launch constraint remains elsewhere.

CHECK YOUR INTUITION

A common misconception

THE TEMPTING CONCLUSION

“Speeding up any task makes the project finish sooner.”

THE MORE USEFUL DISTINCTION

A task with slack can finish earlier without changing its successors' start times. Project acceleration depends on current dependency constraints.

What this explanation leaves out

  • Durations are certain, resources unlimited and dependencies finish-to-start. Real staffing constraints, uncertain durations and quality costs can change the schedule. Multiple paths may become critical after acceleration.
ONE MORE QUESTION

Can there be more than one critical path?

Yes. Equal longest paths can coexist, and shortening only one may leave the others determining the same completion date.

TAKE THE IDEA WITH YOU

Which unfinished task currently determines your actual completion date rather than merely occupying attention?